What is the National Electric Vehicle Infrastructure Formula Program?
The National Electric Vehicle Infrastructure Formula Program is a federal initiative designed to expand publicly accessible EV fast charging infrastructure along designated Alternative Fuel Corridors.
Louisiana is planning to use NEVI funding to support the development of a reliable EV charging network on key highway corridors throughout the state in accordance with the Louisiana State Plan for Electric Vehicle Infrastructure Deployment. For additional information about the NEVI Program, visit the Federal Highway Administration NEVI Formula Program website.
What are Alternative Fuel Corridors?
Alternative Fuel Corridors are highway corridors designated by the Federal Highway Administration as priority routes for alternative fuel infrastructure deployment, including EV charging stations.
Louisiana's AFCs are I-10, I-12, I-20, I-49, I-55, I-59, US-90, LA 3235, and LA-1. For additional information on AFCs, please visit the FHWA Alternative Fuel Corridors website.
What is direct current fast charging?
Direct current fast charging, also referred to as DC fast charging or Level 3 charging, is a high-speed method of charging an electric vehicle. DC fast chargers deliver power directly to the vehicle’s battery and can typically charge a compatible EV to about 80% in 20–30 minutes, depending on the vehicle and charger.
What is Louisiana’s Round 1 NEVI procurement?
Louisiana is allocated federal funding up to $49 million through the NEVI Formula Program. As part of NEVI, DOTD anticipates issuing a competitive RFP in early 2027 for the development, installation, operation and maintenance of publicly accessible DC fast-charging stations.
Round 1 is expected to include 14 NEVI Site Segments. NEVI Site Segments are designated portions of Louisiana's Alternative Fuel Corridors identified by DOTD for potential NEVI-funded charging station deployment. Proposers may submit one or more proposed charging locations within five miles driving distance of a designated NEVI Site Segment, subject to the requirements of the RFP. A detailed methodology for how to measure driving distance will be released as part of the RFP.
Why is DOTD publishing the Round 1 NEVI Site Segment maps in advance of the RFP?
DOTD is publishing the NEVI Site Segment maps in advance of the RFP to help interested parties identify and begin evaluating potential locations for future NEVI-funded charging stations. The maps are intended to support early planning activities by enabling prospective proposers to:
-
Understand the areas targeted for NEVI investment.
-
Identify potential site hosts and properties.
-
Explore potential partnerships.
-
Begin assessing site suitability and local conditions.
-
Start discussions with utilities and other stakeholders.
-
Advance planning activities in preparation for the RFP release.
The maps are provided for advance planning and informational purposes. DOTD may revise the location or boundaries of a NEVI Site Segment before the RFP is issued. The forthcoming RFP will establish the final eligible NEVI Site Segments and all applicable site-location, access, distance and proposal requirements. If there is any inconsistency between these preliminary materials and the RFP, the RFP will control.
What are NEVI Site Segments?
NEVI Site Segments are designated portions of Louisiana's Alternative Fuel Corridors identified by DOTD for potential NEVI-funded charging station deployment during the Louisiana Round 1 NEVI procurement.
Proposed stations must be located within five miles driving distance of a designated NEVI Site Segment. A detailed methodology for how to measure driving distance will be included in the RFP.
What are the minimum requirements for a NEVI-funded charging station?
All stations must meet the federal NEVI standards in 23 Code of Federal Regulations (CFR) Part 680. Based on current federal requirements, anticipated minimum station requirements include the following:
-
Provide at least four direct current fast charging ports per site.
-
Deliver a minimum of 150 kilowatts per charging port.
-
Maintain average annual uptime greater than 97% for each charging port.
-
Be publicly accessible 24 hours a day, 7 days a week, with open-access payment options.
-
Include at least one Combined Charging System Type 1 connector per port.
-
Utilize Open Charge Point Protocol 2.0.1-compliant charging equipment and secure network communications.
-
Support required federal data collection and reporting through the Electric Vehicle Charging Analytics and Reporting Tool.
-
Comply with applicable federal funding and project requirements, including Build America, Buy America, Davis-Bacon prevailing wage requirements, accessibility requirements, environmental requirements and other applicable federal laws and regulations.
Final technical, operating and reporting requirements will be established in the RFP.
Who is eligible to participate in the Round 1 NEVI procurement?
Entities that are not disqualified or debarred by DOTD, the state of Louisiana or the federal government are generally eligible to participate. Detailed proposer eligibility requirements will be established in the RFP.
DOTD anticipates that eligible proposers may submit proposals individually or as part of a team that may include site hosts, contractors, Electric Vehicle Supply Equipment providers, charging-network operators, utilities, operations and maintenance providers and other project partners.
May a proposer submit proposals for more than one NEVI Site Segment?
Yes. Proposers may submit proposals for one or multiple NEVI Site Segments. Specific submission requirements will be provided in the RFP.
What is the Round 1 NEVI procurement schedule?
The exact schedule is yet to be finalized but will be detailed in the RFP. The RFP is expected to be released in early 2027 and proposals are expected to be due in the spring or summer of 2027.